Amazon 7
WORK /
This 1.2M sq ft project is considered a large product facility. The schedule was even more aggressive than Amazon 6. Two shifts, peaking at 41 electricians each, worked with one other electrical contractor to complete the job in 28 days. RMJ’s pre-task planning and material handling processes allowed for a phased move-in.